Paving The Way To Fewer Floods

Ideal Property Group will be upgrading the road and drainage system in Relau, to ease the flooding issue in the surrounding areas.

Ideal Property, which is developing a plot of land nearby in Jalan Kampung Batak, will bear the cost of flood mitigation project in total amount RM2.705mil. Upgrading works are scheduled to start on July 17 and will be completed by July 2018.

The upgrading works would be carried out along the 300m stretch in Jalan Paya Terubong from the Jalan Kampung Batak junction to the Golden Triangle Condominium traffic lights junction. Works include improving the existing drains, upgrading the box culverts and raising the height of Jalan Paya Terubong.